Thank you to all the volunteers working on the raised track , the last section was put in place earlier this month. Some fine adjustments are required and new neoprene pads will be fitted to each pillar top – those just need to be cut to size now.
Thereafter we let track settle and in August fit the bolts to through the bases into the concrete foundations. It is planned to test the track with some of our carriages in August and for locomotive trials by the end of August all going to plan.
Below are pictures of a few of the volunteers who were putting the finishing touches to the track last week.